Put the phases of the classical development cycle in order.
1. Integration and system test 2. Requirements and specification 3. Implementation and unit test 4. Architecture and detailed design
Answer: D
Correct answer: 2, 4, 3, 1
Requirements come first, because nothing can be designed until what the product must do is settled. Architecture and detailed design follow, then implementation with unit testing of the parts, and finally integration and system test of the whole. The order is forced by dependency, and it is the same whether the process is run once as a waterfall or many times in an iterative cycle.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development