A project's schedule slips because the custom board arrives six weeks late. The measure that would have protected it is

  • A.increasing the size of the software team
  • B.developing the software against a development board in the interim
  • C.ordering the board earlier without waiting for the design to be complete
  • D.reducing the scope of the firmware

Answer: B

Almost everything except the board-specific bring-up can be written and tested on an evaluation board with the same processor, which takes the hardware off the software's critical path. It is the standard mitigation for exactly this risk.

No comment is present. Be the first to comment.