The first step of the pre-audit phase is usually

  • A.drawing the plant's energy flow diagram
  • B.securing the commitment of senior management
  • C.installing instruments on the major loads
  • D.reading through the previous twelve months of bills

Answer: B

Correct answer: securing the commitment of senior management

Nothing else is worth starting without it. The auditor needs access, staff time, production data and the cooperation of departments with their own priorities, and the recommendations will need capital. All of that follows from a decision at the top, and an audit begun without it commonly produces a report that is read and shelved.