The baseline of an energy performance measurement is

  • A.the consumption predicted by the nameplate rating of the equipment
  • B.the consumption before the measure, adjusted for the conditions
  • C.the lowest consumption the plant has ever achieved
  • D.the consumption of the best plant in the industry

Answer: B

Savings are the difference between what would have been used and what was used, so the baseline must be adjusted for production, weather and any other driver that has changed. An unadjusted comparison credits the measure with changes it did not cause.