Reducing demand before adding renewable generation is the correct order for a net zero building because
Answer: C
Correct answer: the roof area available for generation is limited
A building has only so much roof and facade to put panels on, so the generation it can carry is capped. If the demand is not reduced first, that ceiling is reached before the balance is struck - and demand measures are usually cheaper per unit than generation besides.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development