Discussion
Maximum demand for billing is conventionally taken as the highest average power over a
Answer: A
Correct answer: fifteen or thirty minute interval
Demand is measured as the highest average power sustained over a defined block, not as an instantaneous peak, because it is sustained load that determines the capacity the network must provide. A momentary starting surge lasting a second heats nothing and is ignored; a half hour at high load does, and is charged for.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development