An additional surcharge on an open access consumer recovers the licensee's

  • A.loss of cross subsidy from that consumer
  • B.expenditure on metering that consumer's supply
  • C.stranded cost of power it had contracted for
  • D.cost of the wires used by that consumer

Answer: C

Long term power purchase agreements were signed to serve a demand that has now left, and the capacity charges continue. The surcharge is payable only where the licensee demonstrates the obligation actually is stranded.