A consumer drawing a maximum demand of 500 kW and consuming 200 000 kWh over a 720 hour month has a load factor of

  • A.40.0 per cent
  • B.72.0 per cent
  • C.55.6 per cent
  • D.27.8 per cent

Answer: C

Correct answer: 55.6 per cent

Load factor is the energy actually taken as a fraction of what would have been taken at the maximum demand throughout: \[ \frac{200\,000}{500 \times 720} = \frac{200\,000}{360\,000} = 0.556. \] A high load factor means the capacity provided is well used, which is why tariffs reward it - the demand charge falls per unit as the load factor rises.