A 100 MW solar plant with a capacity utilisation of 20 per cent generates in a year about
Answer: A
Correct answer: 175 GWh
\[ 100\ \mathrm{MW} \times 8760\ \mathrm{h} \times 0.20 = 175{,}200\ \mathrm{MWh} = 175\ \mathrm{GWh}. \] The 876 GWh offered omits the capacity utilisation factor and assumes the plant runs flat out day and night, which no solar plant does - twenty per cent is about what a well-sited plant in India achieves.