Arrange in correct sequence the yearwise imitation of important systems of extension in India.
I. Community Development Block
II. Democratic Decentralization
III. Community Development Programme
IV. National Extension Service
Codes :
Answer: C
The order is Community Development Programme, National Extension Service, Community Development Block, Democratic Decentralization (III, IV, I, II).
The Community Development Programme began in 1952, the National Extension Service followed in 1953, community development blocks were then taken up as the unit of the programme, and democratic decentralisation (Panchayati Raj) came after the Balwant Rai Mehta Committee in 1957 and was started in 1959.
The other options put Democratic Decentralization first or the block before the programme.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development