Which part of the hydroelectric power plant overcomes the abnormal pressure in the conduit when load on the turbine falls and acts as a reservoir during increase of load on the turbine?
Answer: C
The surge tank is the part of a hydroelectric power plant that overcomes the abnormal pressure in the conduit when the load on the turbine falls and acts as a reservoir when the load increases. When the gates close suddenly, the water hammer is absorbed by the rise of water in the tank, and when the load rises it supplies the extra water at once.
The penstock is the pipe that carries water to the turbine, the dam stores water, and the spillway passes the surplus water. So the third option is the answer.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development