A design shares a large structure between two tasks and takes a mutex round every access. The response time of the higher priority task is
Answer: C
It may arrive while the lock is held and must then wait for the holder to finish, so the longest critical section enters its analysis as a blocking term. Splitting the structure, or passing messages instead, is how that term is removed.