For independent projects under a limited budget, the correct approach is to

  • A.rank by first cost and take the cheapest
  • B.select the combination with the greatest total present worth within the budget
  • C.select the single project with the greatest present worth
  • D.select every project with a positive present worth

Answer: B

Correct answer: select the combination with the greatest total present worth within the budget

Independent projects can be taken in any combination, so the problem is to choose the set that maximises total present worth subject to the budget. This is not the same as taking them in order of present worth: a large project may crowd out two smaller ones worth more between them.