Public hearing is conducted :
Answer: D
The public hearing is conducted after preparation of the draft EIA.
Under the EIA Notification of 2006, the project proponent first prepares a draft EIA report according to the approved terms of reference. The State Pollution Control Board then holds a public hearing near the site, where local people can comment on the draft, and the final EIA report must address the concerns raised before the project is appraised.
The hearing therefore comes after the terms of reference are fixed and the draft is ready, but before environmental clearance, not before site selection or after clearance.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development