Policy monitoring may lead to which of the following actions ?
(i) Strengthening and improving the policy programmes.
(ii) Replanning of the policy programme.
(iii) Cancellation of the policy programme.
Select the correct answer from the codes given below :
Answer: C
Policy monitoring may lead to all three actions, so the answer is (i), (ii), (iii), option C.
Monitoring shows how a programme is working. If it is sound but weak in places, it is strengthened and improved (i). If the design is faulty, it is replanned (ii). If it has failed or has served its purpose, it may be cancelled (iii).
Options A, B and D each leave out at least one of these possible outcomes of monitoring.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development