Evaluated at a project's own internal rate of return, its present worth, annual worth and future worth are all
Answer: A
The three measures differ only by positive conversion factors, so a rate that drives one to zero drives all three there. That is why the rate-of-return and worth criteria never disagree about a single conventional project.