Discussion
Below the crossover rate, the preferred alternative is generally the one with
Answer: C
Correct answer: the higher first cost
At low discount rates, distant receipts retain most of their value, so the larger project - which typically has bigger cash flows further out - wins. As the rate rises those distant flows are penalised more heavily, and above the crossover rate the smaller, quicker-returning project takes the lead.
No comment is present. Be the first to comment.