A project's present worth is +800 at 12 per cent and -400 at 15 per cent. Interpolation puts its internal rate of return near
Answer: A
Correct answer: 14 per cent
Linear interpolation between the two points gives \[ i \approx 12 + 3 \times \frac{800}{800 + 400} = 12 + 2 = 14\ \mathrm{per\ cent}. \] The present worth function is convex rather than straight, so interpolation over a wide interval understates slightly; over three percentage points the error is small.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development