Assertion: the internal rate of return and present worth criteria always agree for a single project. Reason: a positive present worth at the required rate implies the project earns more than that rate.

  • A.the assertion is true but the reason given for it is false
  • B.the assertion is false although the reason offered is a true statement in itself
  • C.both the assertion and the reason are true and the reason explains the assertion
  • D.both the assertion and the reason are true but the reason does not explain the assertion

Answer: C

Correct answer: both the assertion and the reason are true and the reason explains the assertion

Both are true and the reason gives the mechanism. For a conventional cash flow the present worth decreases monotonically with the discount rate and crosses zero once. A positive present worth at the required rate therefore places that rate to the left of the crossing, which is to say below the internal rate - the two criteria are two readings of the same curve.

No comment is present. Be the first to comment.