Drilling and blasting in a limestone quarry is normally followed immediately by
Answer: D
Correct answer: loading and haulage of the broken stone to the crusher
The sequence is drill, blast, load, haul, crush. Blasting reduces the face to fragments a shovel can lift and a crusher can accept, and the crusher then brings the stone down to the size the grinding mill needs. Nothing is ground, blended or burned before the material has been crushed.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development