The sunk cost trap in replacement analysis is the error of
Answer: C
Correct answer: trying to recover past expenditure through the present decision
The trap is the reasoning that runs “we have too much invested in this machine to scrap it now”. Keeping an uneconomic asset does not recover the money already spent; it merely adds further losses to it. The past expenditure is identical under either course and therefore cannot bear on the choice.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development