Discussion
The most frequently overlooked consequence of adding shear walls in a retrofit is
Answer: A
A wall collects a large share of the storey shear and delivers a large overturning moment to its base, and the existing footings were never designed for it. New pile caps or raft extensions are commonly the largest single item of the work.