Anchoring equipment and shelving in a hospital retrofit addresses

  • A.the strength of the structural frame under the design level of shaking
  • B.the natural period of the building and the force it attracts from the spectrum
  • C.the capacity of the foundations under the increased load of the anchorages
  • D.continued function after the earthquake

Answer: D

A hospital whose imaging equipment has shifted and whose supplies are on the floor cannot treat casualties however sound its frame. Restraint of contents is therefore part of a performance objective of continued operation.