Risk assessment in EIA does not involve

  • A.Maximum credible analysis
  • B.Hazard and operability studies
  • C.Preparation of disaster management plan
  • D.Assessment of economic benefit arising out of a project

Answer: D

Risk assessment in an EIA does not involve the assessment of economic benefit arising out of a project. Benefit is dealt with in cost-benefit analysis, not in risk assessment.

Maximum credible loss analysis, hazard and operability studies and the preparation of a disaster management plan are all steps of risk assessment and management for hazardous projects.

Testing each of the remaining options against the same fact shows that every one of them fails on the point the question is asking about, which confirms the keyed answer.