Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.

JobDue dateWork remaining (in days)
M265
N2410
O2810
P315

Which job(s) has/have critical ratio less than unity?

  • A.Job N and Job O
  • B.Job M and Job N
  • C.Job P
  • D.Job O and Job P

Answer: A

The jobs with critical ratio below one are Job N and Job O.

Critical ratio = (time remaining until due date) / (work remaining). On day 20:

\[ \begin{aligned} M &: (26 - 20)/5 = 1.2 \\ N &: (24 - 20)/10 = 0.4 \\ O &: (28 - 20)/10 = 0.8 \\ P &: (31 - 20)/5 = 2.2 \end{aligned} \]

A ratio below 1 means the job is behind schedule. Only N and O qualify. M and P are ahead of schedule, so the options containing them are wrong.