What is the first step in environmental clearance ?

  • A.Project appraisal
  • B.Project identification
  • C.Project monitoring
  • D.Project implementation

Answer: B

The first step is project identification.

A project must first be identified and defined, its nature, size and location, before it can be screened to decide whether it needs environmental clearance and in which category. Only then do scoping, the EIA study, public consultation and appraisal follow, and after clearance come implementation and monitoring.

Appraisal is the expert committee's review near the end of the clearance process, while implementation and monitoring come after clearance is granted.