Part 1 of IS 1893 deals with
Answer: A
The parts divide the field by structure type: Part 1 covers general provisions and buildings, Part 2 liquid retaining tanks, Part 3 bridges and retaining walls, and Part 4 industrial structures. Part 1 carries the zone map and the zone factors that the other parts refer to.