One of the major factor incorporated in the process framework of RUP (Rational Unified Process) model is :

  • A.Iterative and incremental
  • B.Iterative and continuous
  • C.Incremental and validations
  • D.Continuous and validations

Answer: A

The factor is iterative and incremental development.

The Rational Unified Process divides a project into four phases, inception, elaboration, construction and transition, each carried out in a series of iterations. Every iteration passes through requirements, analysis, design, implementation and testing and adds a further increment of working software. RUP is also described as use-case driven and architecture-centric.

'Continuous' and 'validations' are not the terms in which the RUP framework is defined; validation happens within each iteration but is not its organising principle.