Which model assumes that effort and development time are functions of product size alone ?
Answer: A
The model is Basic COCOMO.
Boehm's Basic COCOMO estimates effort and development time from product size alone:
\[ E = a\,(KLOC)^{b}, \quad D = c\,E^{d} \]
with constants depending only on whether the project is organic, semi-detached or embedded.
Intermediate COCOMO multiplies the estimate by an effort adjustment factor from 15 cost drivers (product, hardware, personnel and project attributes), and Detailed COCOMO applies those drivers phase by phase, so neither depends on size alone. 'COCOMO' on its own names the whole family.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development