Which is the correct evolutionary path of five level capability maturity model ?

  • A.initial, defined, repeatable, managed, optimizing
  • B.initial, repeatable, defined, managed, optimizing
  • C.initial, defined, managed, optimizing, repeatable
  • D.initial, repeatable, managed, defined, optimizing

Answer: B

The correct path is initial, repeatable, defined, managed, optimizing.

  1. Initial: the process is ad hoc and chaotic.
  2. Repeatable: basic project management lets earlier successes be repeated.
  3. Defined: the process is documented and standardised across the organisation.
  4. Managed: the process and products are measured and controlled quantitatively.
  5. Optimizing: continuous process improvement through feedback and innovation.

Options A and C put 'defined' before 'repeatable', and D puts 'managed' before 'defined'; each breaks the order of the five SEI CMM levels.