The maturity levels used to measure a process are

  • A.Initial, Repeatable, Defined, Managed, Optimized.
  • B.Primary, Secondary, Defined, Managed, Optimized.
  • C.Initial, Stating, Defined, Managed, Optimized.
  • D.None of the above

Answer: A

The maturity levels of the Capability Maturity Model used to measure a process are Initial, Repeatable, Defined, Managed and Optimizing. They run from level 1 where the process is ad hoc to level 5 where it is continuously improved.

The names 'Primary' and 'Secondary' and 'Stating' in the other options are not levels of the model, so the second and third lists are wrong, and 'None of the above' is wrong because the first list gives the levels correctly.