Assertion (A): Belite-rich cement has not displaced ordinary Portland cement despite its lower emissions.
Reason (R): Belite hydrates slowly, so early strength is much lower than the construction industry expects.
Answer: A
Both are true and the reason gives the obstacle: construction schedules are built around early strength, and a binder that takes months to reach a usable figure changes the economics of a project far more than the cement price does.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development