The Liu and Layland utilisation bound for \( n \) tasks under rate monotonic scheduling is
Answer: D
It falls from 1.0 for one task through 0.828 for two and 0.780 for three toward 0.693 as the number grows. A set below the bound is certainly schedulable; a set above it may still be, and response time analysis must then be used.