Earliest deadline first assigns the processor to the ready task with
Answer: D
Correct answer: the nearest absolute deadline
Earliest deadline first is dynamic: the priority is recomputed at each release from the absolute deadline, so a task’s priority rises as its deadline approaches. That is what makes it optimal on one processor, meeting every deadline whenever the utilisation is at most unity.
No comment is present. Be the first to comment.