Earliest deadline first assigns the processor to the ready task with

  • A.the shortest period
  • B.the shortest remaining execution time
  • C.the largest laxity
  • D.the nearest absolute deadline

Answer: D

Correct answer: the nearest absolute deadline

Earliest deadline first is dynamic: the priority is recomputed at each release from the absolute deadline, so a task’s priority rises as its deadline approaches. That is what makes it optimal on one processor, meeting every deadline whenever the utilisation is at most unity.