Comparing earliest deadline first with rate monotonic, the dynamic scheme's chief drawback is
Answer: B
Under overload a fixed priority system sheds the lowest priority tasks predictably, whereas earliest deadline first can miss deadlines across the whole set as everything becomes urgent at once. Its utilisation bound is the higher of the two, at unity.