A designer halves the period of the highest priority task in a schedulable set. The set is now
Answer: D
Correct answer: possibly unschedulable, the interference on everything below having doubled
Halving the period doubles both that task’s utilisation and the number of times it preempts everything below it in the analysis window. The task itself is unaffected, being highest priority, but every other task now suffers twice the interference from it, and the set must be reanalysed.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development