Consider the following statements about scheduling.

1. A utilisation above unity is always infeasible   2. The rate monotonic bound is necessary and sufficient   3. Earliest deadline first is optimal on one processor

  • A.1, 2 and 3 are all correct statements about scheduling
  • B.1 and 2 only are correct
  • C.2 and 3 only are correct
  • D.1 and 3 only are correct

Answer: D

Correct answer: 1 and 3 only are correct

Statements 1 and 3 are correct: utilisation above unity is infeasible for any algorithm, and earliest deadline first is optimal on one processor. Statement 2 overstates the rate monotonic bound, which is sufficient but not necessary - a set exceeding it may still meet every deadline, which is why response time analysis exists.