An engineer reports a task set of utilisation 1.4 as schedulable under earliest deadline first. The proper response is
Answer: C
Correct answer: the set demands more processor than exists and cannot be scheduled
A utilisation of 1.4 means the work requires forty per cent more processor time than the hardware provides, and no algorithm can create it. Earliest deadline first is optimal, but optimality means it succeeds whenever success is possible - and here it is not.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development