A task set is schedulable in analysis but misses deadlines on the target. The most likely omission is
Answer: D
Handlers run above every task and steal time that no task's execution figure includes, so a busy interrupt source can invalidate an otherwise sound analysis. Charging the handler load as a highest-priority pseudo-task is the standard correction.