Initial setting time is measured as the interval from adding water until
Answer: C
It marks the point at which the paste is no longer usefully workable, so it sets a practical limit on how long concrete can be transported and placed. Final set is measured later with a different attachment. Both figures are quoted because each has a different practical meaning.