A machine that has stood idle in a damp place should have its insulation
Answer: C
Correct answer: dried out before any high-voltage test is applied
Absorbed moisture lowers the insulation resistance and provides paths for surface tracking, so applying test voltage to a damp winding may puncture insulation that would have been perfectly sound once dry. Drying and re-testing the insulation resistance and polarisation index comes first; the withstand test comes only after both are acceptable.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development