A does 20% less work than B. If A can complete a piece of work in \(7\frac{1}{2}\) hours then B can do it in
Answer: A
A does 20% less work than B, so A's rate is 0.8 of B's. If A takes 7.5 hours, B takes 7.5 x 0.8 = 6 hours, option A.
The other options come from using 1.25 or other wrong factors, such as \(5\frac{1}{2}\), \(6\frac{1}{2}\) and \(6\frac{3}{4}\) hours.
Work is rate times time, so with A's rate at 80 per cent of B's, B takes 80 per cent of A's time. Then 7.5 x 0.8 = 6 hours. The tempting answer of 9.375 hours comes from dividing by 0.8 instead of multiplying, and it is not offered. The other options come from similar slips.
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development