In carrying out the test that yields the copper loss, the engineer applies
Answer: A
Correct answer: reduced voltage giving rated current in the shorted winding
In the short circuit test one winding is shorted and the applied voltage raised only until rated current flows - a few per cent of rated voltage. The flux, and therefore the core loss, is negligible at that voltage, so the wattmeter reads essentially the full-load copper loss, and the readings also give the equivalent series impedance.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development