Which of the following estimates is applicable for an additional work that is necessary for the project while in progress?

  • A.Quantity estimate
  • B.Revised estimate
  • C.Supplementary estimate
  • D.Detailed estimate

Answer: C

A supplementary estimate is prepared for additional work that becomes necessary while the project is in progress, and that was not provided in the original sanction. A revised estimate is made when the sanctioned estimate is going to be exceeded by the original work itself, a detailed estimate is the full estimate made from the drawings before the work starts, and a quantity estimate lists only the quantities of the items.