Which of the following estimates is applicable for an additional work that is necessary for the project while in progress?
Answer: C
A supplementary estimate is prepared for additional work that becomes necessary while the project is in progress, and that was not provided in the original sanction. A revised estimate is made when the sanctioned estimate is going to be exceeded by the original work itself, a detailed estimate is the full estimate made from the drawings before the work starts, and a quantity estimate lists only the quantities of the items.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development