If 10 men can do a piece of work in 12 days, how many men are needed to do the same work in 8 days?

  • A.12 men
  • B.15 men
  • C.18 men
  • D.20 men

Answer: B

The total work is fixed in man-days.

\[ 10 \times 12 = 120 \text{ man-days} \]

\[ \frac{120}{8} = 15 \text{ men} \]

Men and days are inversely proportional for a fixed job.