10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
Answer: C
Let W be woman's work, C be child's work. From the problem, \(10W \times 7 = 10C \times 14 \Rightarrow 70W = 140C \Rightarrow W=2C\). Total work = \(10W \times 7 = 10(2C) \times 7 = 140C\). We need time for 5 women and 10 children. Their combined rate = \(5W+10C = 5(2C)+10C = 10C+10C=20C\). Time = Total work / Rate = 140C / 20C = 7 days.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development