A and B can do a work in 45 and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave?
Answer: C
Let the total work be LCM(45,40)=360 units. A's rate=8, B's rate=9 units/day. B worked alone for the last 23 days, so work done by B alone = \(23 \times 9 = 207\) units. Work done by A and B together = \(360 - 207 = 153\) units. Combined rate of A and B = 8+9=17 units/day. Time they worked together = 153/17 = 9 days. So, A left after 9 days.
No comment is present. Be the first to comment.
Loading…
Post your comment
Please log in or register to post a comment.
Examination Categories
- SSC Exams
- Banking Exams
- Teaching Exams
- Civil Services Exams
- Railways Exams
- Engineering Recruitment Exams
- Defence Exams
- State Government Exams
- Police Exams
- Insurance Exams
- Nursing Exams
- Other Government Exams
- NRA CET
- PG Entrance Exams
- Campus Placement
- MBA Entrance Exams
- CUET and UG Entrance
- Judiciary Exams
- Regulatory Body Exams
- Software Development