A can do a piece of work in 12 days and B in 18 days. Working together, in how many days will they finish it ?
Answer: C
Correct answer: 7.2 days
Add the daily rates rather than the times.
\[\frac{1}{12} + \frac{1}{18} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36}\]
Working at five thirty-sixths of the job per day, they need
\[\frac{36}{5} = 7.2 \text{ days}\]