A can do a piece of work in 12 days and B in 18 days. Working together, in how many days will they finish it ?

  • A.7.2 days
  • B.7.5 days
  • C.8 days
  • D.9 days

Answer: C

Correct answer: 7.2 days

Add the daily rates rather than the times.

\[\frac{1}{12} + \frac{1}{18} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36}\]

Working at five thirty-sixths of the job per day, they need

\[\frac{36}{5} = 7.2 \text{ days}\]