A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

  • A.9 1/5 days
  • B.9 2/5 days
  • C.9 3/5 days
  • D.10 days

Answer: C

Work in rates: someone who finishes a job in \( n \) days does \( \tfrac{1}{n} \) of it a day, and rates add.

\[ \frac{1}{16} + \frac{1}{12} + \frac{1}{C} = \frac{1}{4} \]

\[ \frac{1}{C} = \frac{12}{48} - \frac{3 + 4}{48} = \frac{5}{48} \]

\[ C = \frac{48}{5} = 9\tfrac{3}{5} \text{ days} \]