A team proposes skipping conceptual design to save schedule. The proposal is
Answer: C
Correct answer: Unsound; it commits most lifetime cost
Skipping the phase does not remove the decisions it makes; it only makes them implicitly, without exploring alternatives, while still committing the great majority of the lifetime cost. The schedule saved is a few per cent of the budget, and the exposure is the other sixty-five. A derivative programme can legitimately run a much shorter conceptual phase, since the configuration is inherited and only the changes need exploring - but that is compressing the phase, not skipping it.